Abstract: Circulation tests were conducted to test the connectivity between the injection well 16A(78)-32 and the production well 16B(78)-32 in July 2023 at Utah FORGE site. The test results show that there is a connection between these two wells. Around 7750 bbl of water was injected during the circulation […]
Title: Analysis of Circulation Tests and Well Connections at Utah FORGE
Authors: Pengju XING, Kevin ENGLAND, John MCLENNAN, Rob PODGORNEY, Joseph MOORE
Key Words: circulation test, FORGE, connection